A plain guide to permitted development in England: extensions, lofts, outbuildings, where the rules do not apply, and how to check with a certificate.

Updated 15/10/2026. Every fact links to its source at the end of the page.

What permitted development means

Permitted development rights are a national grant of planning permission. They allow certain building works and changes of use without a planning application 6. This guide covers England only.

The rules below apply to houses. They do not apply to flats and maisonettes 1. Planning Portal’s pages are an introduction, not the full legal text, so check with your local planning authority before you start 1.

Extensions

For all extensions, these limits apply 1:

  • Extensions and other buildings together can cover no more than half the land around the original house.
  • The extension cannot be higher than the highest part of the existing roof.
  • Eaves cannot be higher than the existing eaves. Within 2m of a boundary, eaves must be 3m or lower.
  • No extension forward of the principal elevation, or the side elevation where it fronts a highway.
  • Exterior materials must have a similar appearance to the existing house.

Single-storey rear extensions can project 4m beyond the original rear wall on a detached house, or 3m on other houses. They can be up to 4m high 1.

Side extensions must be single storey, up to 4m high, and no wider than half the width of the original house 1.

Extensions of more than one storey cannot project more than 3m beyond the original rear wall. They must not be within 7m of the boundary opposite the rear wall 1.

Larger single-storey rear extensions

Outside designated land and Sites of Special Scientific Interest, the rear limit rises to 8m for a detached house and 6m for other houses 1. This needs prior approval. You apply to the local authority, which consults your adjoining neighbours 2. If neighbours raise concerns or objections, the authority decides whether the effect on their amenity is acceptable 2.

Lofts

For a loft conversion that enlarges the roof, the limits are 40 cubic metres for terraced houses and 50 cubic metres for other houses 3. This includes any earlier enlargement 3. Other conditions include 3:

  • The enlargement cannot be higher than the existing roof.
  • On the principal elevation, where it fronts a highway, it cannot extend beyond the existing roof slope.
  • It must be set back at least 20cm from the original eaves, as far as practicable.
  • Materials must be similar in appearance to the existing house.
  • Side-facing windows must be obscure-glazed. If they open, the opening part must be at least 1.7m above the floor.
  • No verandas, balconies or raised platforms.

Outbuildings

Outbuildings and garages must be single storey with eaves no higher than 2.5m 4. The overall height limit is 4m with a dual-pitched roof, or 3m for any other roof 4. Within 2m of a boundary, the maximum height is 2.5m 4. You cannot put an outbuilding forward of the wall forming the principal elevation 4. The rules do not cover use as separate self-contained living accommodation 4.

Where permitted development does not apply

  • Flats and maisonettes. The house rules do not apply to them 13.
  • Conservation areas and other designated land. Conservation areas count as “Article 2(3) designated land” 1. There, all side extensions and all rear extensions of more than one storey need householder planning permission, and exterior cladding is not allowed 1. Loft enlargements under the usual rules do not apply there either 3.
  • Listed buildings. Any outbuilding within the curtilage of a listed building needs planning permission 4. Works to a listed building may also need listed building consent, which is separate 6.
  • Article 4 directions, conditions and other limits. A planning condition, an Article 4 direction or another restriction can remove permitted development rights 1. An Article 4 direction means the work needs a planning application 6. A local planning authority or the Secretary of State can make a direction withdrawing specific rights in a defined area 6.

Check first with a lawful development certificate

If it is unclear whether permitted development applies, you can apply for a lawful development certificate 6. It is a legal document stating whether a past, present or future use or building work is lawful 5. It can settle whether a permitted development proposal is legal 5. It is not a replacement for planning permission, and anything it does not cover still needs separate permission 5.

Where to get help

  • Your local planning authority. Planning Portal says to contact it if in doubt, and that councils may charge for pre-application advice 1.
  • The government’s technical guidance for householders, which covers England. It was last updated on 10 September 2019, so check that the rules have not changed 7.

Sources

  1. Planning permission - Extensions Planning Portal (planningportal.co.uk). Checked 14/10/2026.
  2. Prior approval - Extensions Planning Portal (planningportal.co.uk). Checked 14/10/2026.
  3. Planning permission - Loft conversion Planning Portal (planningportal.co.uk). Checked 14/10/2026.
  4. Planning permission - Outbuildings Planning Portal (planningportal.co.uk). Checked 14/10/2026.
  5. Lawful Development Certificate - Consent types Planning Portal (planningportal.co.uk). Checked 14/10/2026.
  6. When is permission required? GOV.UK (Ministry of Housing, Communities and Local Government planning practice guidance) (gov.uk). Page updated 26/07/2023. Checked 14/10/2026.